Abell & Cleland House
Project Location
30, John Islip Street, Westminster, London, SW1P 4LHMain Contractor
Berkeley Homes Central LondonProject Background
Development is the new building construction of 275, 1-3 bedroom luxury apartments on a site in the heart of Westminster that was previously occupied by vacant government office buildings.
Project was started in a May 2013 and is due for completion in the summer/Autumn of 2016.
Abel House consists of approximately 6000m of sealant work and Cleland House of 8000m approximately.
Application
Requirement was to seal horizontal and vertical external expansion joints in the precast panels (dual sealed) up to 30mm wide and a single seal around window frames.
Some of the sealant application had to be done via abseil, due to access constraints.